0
$\begingroup$

Consider two columns.

Column A has total cost per day, Column B has units bought that day. The marginal cost of each unit is increasing because of limited supply.

My goal is to estimate total possible units under a certain budget.

What I did for this was run a LOGEST estimation to get the information in the form of cost = b+ m^units My reason for doing this is because of the increasing marginal cost per unit.

I got the function : y = 1.00077^x + 0.24

But when maximizing it, the numbers I'm getting for units are too small under this budget.

I also ran a LINEST and got that each unit bought increases the cost per unit by approximately 0.0005814009591 $. I have been unable to make a model that uses this estimation.

Any suggestion or different approach will be much appreciated, Thanks.

$\endgroup$

1 Answer 1

1
$\begingroup$

I think you are making this harder than this needs to be from a reasoning standpoint. Given a budget M, you are trying to maximize your total expenditure. You have just one input cost, being marginal material cost of the additional good. There is no trade-off between inputs, so "maximizing" in this sense just means how much you can buy given M, which will end up being simple algebra rather than some more difficult Lagrange calculus needed for multivariate constraint functions.

The issue with your LINEST model is that either your dependent variable is the marginal cost, not the total cost (as needed for your objective), or you are interpreting it incorrectly. If the former, rerun the regression with the data you referenced. If you used the two columns of data that you referenced then your interpretation I wrong and should be as follows: your coefficient β(1) would then just be the estimated price per item (an intercept shouldn't exist as no fixed costs are present), with the independent variable being the number of units, and the dependent being the total cost for that day. If you use this model, then your given M should be plugged into the left side of the equation and then solve for the number of units algebraically. Keep in mind that if you end up with, say, x=12.7, then you should round down, as 13 units would be unattainable under the constraint.

I would consider using the log function, however, due to the increasing MC like you mentioned above. For your log function, follow the same algebra as above, solving for x=units attainable under the y=M constraint. Use a calculator for that one, no one wants to do log base 1.77 of a number in their head.

$\endgroup$

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Not the answer you're looking for? Browse other questions tagged or ask your own question.